    General information
    Attribute Value
    Production licence
    Name of the production licence
    646
    NPDID production licence
    Norwegian Offshore Directorate's unique id for production licences
    21559761
    Status
    Current status of production licence. Example of legal values: ACTIVE, INACTIVE
    INACTIVE
    Main area
    Name of the area on the Norwegian Continental Shelf where the wellbore is located. Example of legal values: Barents Sea, Norwegian Sea, North Sea
    Norwegian sea
    Licensing activity
    Name of the licensing activity the production licence was awarded in.
    TFO2011
    Date granted
    Date the production licence was granted by the Norwegian authorities.
    03.02.2012
    Date valid to
    Date the production licence is valid to.
    03.02.2015
    Stratigraphical
    Indicates if the licence has vertical limitations based on stratigraphy. 'NO' means no such limitations, 'YES OR PARTLY' means that either whole or parts of the licence has such limitations.
    NO
    Original area [km2]
    Original area of the production licence in square kilometres.
    69
    Current area [km2]
    Current area of the production licence in square kilometres.
    0
  • Phases

    Phases
    Date phase valid from
    Date phase valid to
    Phase
    03.02.2012
    03.02.2019
    INITIAL
    04.02.2019
    03.02.2020
    INITIAL EXTENDED
  • Licensees — current

    Licensees — current
    Date valid from
    Company longname
    Interest [%]
  • Operatorship — current

    Operatorship — current
    Date valid from
    Company longname
  • Area – current

    Area – current
    Date valid from
    Block name
    Polygon number
    Polygon area
    [km2]
    Vertical limitations
  • Work program (initial phase)

    Work program (initial phase)
    Work obligation
    Decision
    Task status
    Expiry date
    Wellbore if drilled
    Seismic acquisition
    Approved
    Seismic reprocessing
    Approved
    Study of geology and geophysics
    Approved
    Decision to drill
    Not to be drilled
    03.02.2015
    Drill exploration well
    Not to be drilled
    (BoK) Decision to concretize
    Dropped
    03.02.2017
    Conceptual studies
    Dropped
    (BoV) Decision to continue
    Dropped
    03.02.2019
    (PDO) Prepare plan for development
    Dropped
    (PDO) Decision to submit plan for development
    Dropped
    03.02.2020
    Decision to enter extension period
    Dropped
    03.02.2020
  • Conditions (production phase)

    Conditions (production phase)
    Work task
    Decision
    Description (norwegian)
    Task status
    Expiry date
  • Mortgages from the Petroleum register – current (in Norwegian only)

    Mortgages from the Petroleum register – current (in Norwegian only)
    Dokument nummer
    Registreringsdato
    Utdrag av dokument
    6981
    02.04.2013
    Noreco Norway AS pantsetter sin 20 % deltakerandel i utvinningstillatelsen til fordel for SpareBank 1 SR-Bank ASA. Første prioritet panteobligasjon stor NOK 1,240,000,000, skriver norske kroner enmilliardtohundreogførtimillioner 00/100. Pantsetter har ikke rett til å overdra eller foreta ytterligere pantsettelser av pantsatte objekt uten skriftlig samtykke fra panthaver. Olje- og energidepartementet har i brev av 9.1.2013 gitt samtykke i medhold av petroleumsloven § 6-2 første ledd. Pantsettelsen utgjør et såkalt krysspant.
    7726
    03.03.2014
    Olje- og energidepartementet bekrefter i brev datert 26.2.2014 at initiell periode forlenges til 3.2.2020, jf. petroleumsloven § 3-9 første ledd.
  • Wellbores – exploration, drilled in the production licence

    Wellbores – exploration, drilled in the production licence
    Wellbore name
    Entered date
    Completed date
    Purpose
    Content
  • Wellbores – development, drilled in the production licence

    Wellbores – development, drilled in the production licence
    Wellbore name
    Entered date
    Completed date
    Purpose - planned
  • Wellbores – other, drilled in the production licence

    Wellbores – other, drilled in the production licence
    Wellbore name
    Entered date
    Completed date
    Purpose
  • Licensees — full history

    Licensees — full history
    Date valid from
    Date valid to
    Company longname
    Interest [%]
    15.05.2013
    03.02.2015
    40.000000
    20.000000
    20.000000
    20.000000
    31.12.2012
    14.05.2013
    40.000000
    20.000000
    20.000000
    20.000000
    24.03.2012
    30.12.2012
    40.000000
    20.000000
    20.000000
    20.000000
    03.02.2012
    23.03.2012
    40.000000
    20.000000
    20.000000
    20.000000
  • Operatorship — full history

    Operatorship — full history
    Date valid from
    Date valid to
    Company longname
    24.03.2012
    03.02.2015
    03.02.2012
    23.03.2012
  • Area – full history

    Area – full history
    Date valid from
    Date valid to
    Block name
    Polygon number
    Polygon area
    [km2]
    Vertical limitations
    03.02.2012
    03.02.2015
    6507/8
    1
    40
    6507/9
    2
    29
  • Licensees – transfers

    Licensees – transfers
    Date valid from
    Transfer direction
    Type of change
    Company name
    Transferred interest [%]
    15.05.2013
    TO
    CHANGE OF COMPANY NAME
    20.000000
    FROM
    CHANGE OF COMPANY NAME
    20.000000
    31.12.2012
    TO
    TRANSFER
    20.000000
    FROM
    TRANSFER
    20.000000
    24.03.2012
    FROM
    CHANGE OF COMPANY NAME
    40.000000
    TO
    CHANGE OF COMPANY NAME
    40.000000
  • Status reports

    Status reports
    Document name
    Document format
    Document size [MB]