    General information
    Attribute Value
    Production licence
    Name of the production licence
    405
    NPDID production licence
    Norwegian Offshore Directorate's unique id for production licences
    4237284
    Factmaps in new window
    Status
    Current status of production licence. Example of legal values: ACTIVE, INACTIVE
    ACTIVE
    Main area
    Name of the area on the Norwegian Continental Shelf where the wellbore is located. Example of legal values: Barents Sea, Norwegian Sea, North Sea
    North sea
    Licensing activity
    Name of the licensing activity the production licence was awarded in.
    TFO2006
    Date granted
    Date the production licence was granted by the Norwegian authorities.
    16.02.2007
    Date valid to
    Date the production licence is valid to.
    01.12.2036
    Stratigraphical
    Indicates if the licence has vertical limitations based on stratigraphy. 'NO' means no such limitations, 'YES OR PARTLY' means that either whole or parts of the licence has such limitations.
    NO
    Original area [km2]
    Original area of the production licence in square kilometres.
    625
    Current area [km2]
    Current area of the production licence in square kilometres.
    11
  • Phases

    Phases
    Date phase valid from
    Date phase valid to
    Phase
    16.02.2007
    16.02.2013
    INITIAL
    17.02.2013
    16.02.2016
    INITIAL EXTENDED
    17.02.2016
    01.12.2016
    INITIAL EXTENDED
    02.12.2016
    01.12.2036
    PRODUCTION
  • Licensees — current

    Licensees — current
    Date valid from
    Company longname
    Interest [%]
    03.11.2022
    70.000000
    -
    15.000000
    -
    15.000000
  • Operatorship — current

    Operatorship — current
    Date valid from
    Company longname
    31.05.2022
  • Area – current

    Area – current
    Date valid from
    Block name
    Polygon number
    Polygon area
    [km2]
    Vertical limitations
    02.12.2020
    8/10
    1
    11
  • Work program (initial phase)

    Work program (initial phase)
    Work obligation
    Decision
    Task status
    Expiry date
    Wellbore if drilled
    Seismology - collecting, reprocessing, interpretation
    Approved
    Decision to drill
    Will be drilled
    16.08.2009
    Drilling
    Approved
    8/10-4 S
    (BoV) Decision to continue
    Approved
    01.12.2015
    (PDO) Decision to submit plan for development
    Approved
    01.12.2016
    Decision to enter extension period
    Approved
    01.12.2016
  • Conditions (production phase)

    Conditions (production phase)
    Work task
    Decision
    Description (norwegian)
    Task status
    Expiry date
    Decision to drill
    Område 2 - Cassidy
    Will be drilled
    01.12.2017
    (BoK) Decision to concretize
    Område 2 - Cassidy
    Dropped
    01.12.2019
    Drill exploration well
    Område 2 - Cassidy
    Approved
    Decision to drill
    Område 3 - Bonanza og Durango
    Not to be drilled
    01.12.2020
    (BoK) Decision to concretize
    Område 3 - Bonanza og Durango
    Dropped
    01.12.2020
    (BoV) Decision to continue
    Område 2 - Cassidy
    Dropped
    01.12.2020
    Drill exploration well
    Område 3 - Bonanza og Durango
    Not to be drilled
    Conceptual studies
    Område 2 - Cassidy
    Dropped
    (BoV) Decision to continue
    Område 3 - Bonanza og Durango
    Dropped
    01.12.2021
    (PDO) Decision to submit plan for development
    Område 2 - Cassidy
    Dropped
    01.12.2021
    (PDO) Submit plan for development
    Område 2 - Cassidy
    Dropped
    01.12.2021
    Conceptual studies
    Område 3 - Bonanza og Durango
    Dropped
    (PDO) Prepare plan for development
    Område 2 - Cassidy
    Dropped
    (PDO) Decision to submit plan for development
    Område 3 - Bonanza og Durango
    Dropped
    01.12.2022
    (PDO) Submit plan for development
    Område 3 - Bonanza og Durango
    Dropped
    01.12.2022
    (PDO) Prepare plan for development
    Område 3 - Bonanza og Durango
    Dropped
  • Mortgages from the Petroleum register – current (in Norwegian only)

    Mortgages from the Petroleum register – current (in Norwegian only)
    Dokument nummer
    Registreringsdato
    Utdrag av dokument
    14555
    15.11.2019
    DNO North Sea (Norge) AS pantsetter sin 15 % deltakerandel i utvinningstillatelsen til fordel for Danske Bank A/S stor USD 850 000 000, skriver Eight Hundred and Fifty Million United States Dollars. Pantsetter har ikke rett til å overdra eller foreta ytterligere pantsettelser av pantsatte objekt uten skriftlig samtykke fra panthaver. Olje- og energidepartementet har i brev av 4.11.2019 gitt samtykke i medhold av petroleumsloven § 6-2 første ledd. Pantsettelsen utgjør et såkalt krysspant.
    15026
    23.12.2019
    Pantobligasjon pålydende stor USD 850 000 000, skriver Eight Hundred and Fifty Million United States Dollars (dok.nr 14555) overføres fra DNO North Sea (Norge) AS til DNO Norge AS. Overføring av pantobligasjonen er godkjent av Danske Bank A/S 13.12.2019. Olje- og energidepartementet har i brev av 16.12.2019 gitt samtykke til overføring av pantobligasjonen, jf. petroleumsloven § 6-2 første ledd. Pantsettelsen utgjør et såkalt krysspant.
    16916
    17.06.2022
    Sval Energi AS pantsetter sin 40 % deltakerandel i tillatelsen til fordel for DNB Bank ASA as Security Agent for a syndicate of banks. Pantobligasjon stor USD 840 000 000, skriver United States Dollars Eighthundreandfortymillion.Pantsetter har ikke rett til å overdra eller foreta ytterligere pantsettelser av pantsatte objekt uten skriftlig samtykke fra panthaver.Olje- og energidepartementet har i brev av 9.6.2022 gitt samtykke i medhold av petroleumsloven § 6-2 første ledd. Pantsettelsen utgjør et såkalt krysspant.
    17258
    19.10.2022
    Sval SENAS AS pantsetter sin 30 % deltakerandel i tillatelsen til fordel for DNB Bank ASA as Security Agent for a syndicate of banks. Pantobligasjon stor USD 1,050,000,000, skriver One billion fifty million United States Dollars.Pantsetter har ikke rett til å overdra eller foreta ytterligere pantsettelser av pantsatte objekt uten skriftlig samtykke fra panthaver.Olje- og energidepartementet har i brev av 19.10.2022 gitt samtykke i medhold av petroleumsloven § 6-2 første ledd. Pantsettelsen utgjør et såkalt krysspant.
    17394
    16.11.2022
    Sval Energi AS pantsatte en 40 % deltakerandel i utvinningstillatelsen til fordel for DNB Bank ASA as Security Agent for a syndicate of banks, pantobligasjon stor USD 840 000 000, skriver United States Dollars Eight hundred and forty million, 16.6.2022 (dok.nr. 16916). Pantebeløpet forhøyes til USD 1 620 000 000, skriver One billion six hundred and twenty million United States Dollars. Panteforhøyelsen er godkjent av Sval Energi AS ved påtegning på pantedokument
    17393
    16.11.2022
    Sval SENAS AS pantsatte en 30 % deltakerandel i utvinningstillatelsen til fordel for DNB Bank ASA as Security Agent for a syndicate of banks, pantobligasjon stor USD 1 050 000 000, skriver One billion fifty million United States Dollars, 16.10.2022 (dok.nr. 17258). Pantebeløpet forhøyes til USD 1 620 000 000, skriver One billion six hundred and twenty million United States Dollars. Panteforhøyelsen er godkjent av Sval Energi AS ved påtegning på pantedokument.
  • Wellbores – exploration, drilled in the production licence

    Wellbores – exploration, drilled in the production licence
    Wellbore name
    Entered date
    Completed date
    Purpose
    Content
    27.10.2011
    18.12.2011
    APPRAISAL
    DRY
    22.12.2011
    02.01.2012
    APPRAISAL
    NOT APPLICABLE
    15.08.2011
    27.10.2011
    WILDCAT
    OIL
    06.03.2014
    24.05.2014
    WILDCAT
    DRY
    04.01.2014
    04.03.2014
    WILDCAT
    DRY
    29.05.2014
    16.07.2014
    WILDCAT
    DRY
    04.12.2018
    04.01.2019
    WILDCAT
    DRY
  • Wellbores – development, drilled in the production licence

    Wellbores – development, drilled in the production licence
    Wellbore name
    Entered date
    Completed date
    Purpose - planned
    27.07.2018
    20.10.2018
    PRODUCTION
    07.04.2022
    16.04.2022
    PRODUCTION
    29.07.2018
    25.09.2018
    INJECTION
    25.07.2018
    19.08.2018
    PRODUCTION
    20.08.2018
    31.08.2018
    PRODUCTION
  • Wellbores – other, drilled in the production licence

    Wellbores – other, drilled in the production licence
    Wellbore name
    Entered date
    Completed date
    Purpose
    07.07.2013
    08.07.2013
    SOIL DRILLING
    27.09.2015
    30.09.2015
    SHALLOW GAS
  • Licensees — full history

    Licensees — full history
    Date valid from
    Date valid to
    Company longname
    Interest [%]
    03.11.2022
    70.000000
    15.000000
    15.000000
    30.09.2022
    02.11.2022
    40.000000
    30.000000
    15.000000
    15.000000
    31.05.2022
    29.09.2022
    40.000000
    30.000000
    15.000000
    15.000000
    19.12.2019
    30.05.2022
    40.000000
    30.000000
    15.000000
    15.000000
    21.05.2019
    18.12.2019
    40.000000
    30.000000
    15.000000
    15.000000
    04.12.2018
    20.05.2019
    40.000000
    30.000000
    15.000000
    15.000000
    22.12.2017
    03.12.2018
    40.000000
    30.000000
    15.000000
    15.000000
    09.12.2016
    21.12.2017
    40.000000
    30.000000
    15.000000
    15.000000
    13.02.2013
    08.12.2016
    40.000000
    30.000000
    15.000000
    15.000000
    28.02.2011
    12.02.2013
    40.000000
    30.000000
    15.000000
    15.000000
    01.01.2009
    27.02.2011
    40.000000
    30.000000
    15.000000
    15.000000
    16.02.2007
    31.12.2008
    40.000000
    30.000000
    30.000000
  • Operatorship — full history

    Operatorship — full history
    Date valid from
    Date valid to
    Company longname
    31.05.2022
    04.12.2018
    30.05.2022
    22.12.2017
    03.12.2018
    16.02.2007
    21.12.2017
  • Area – full history

    Area – full history
    Date valid from
    Date valid to
    Block name
    Polygon number
    Polygon area
    [km2]
    Vertical limitations
    02.12.2020
    8/10
    1
    11
    01.12.2019
    01.12.2020
    8/10
    1
    19
    01.01.2018
    30.11.2019
    8/10
    1
    71
    14.02.2015
    31.12.2017
    8/10
    1
    101
    16.02.2007
    13.02.2015
    8/8
    4
    22
    8/10
    5
    375
    7/12
    2
    28
    8/11
    6
    37
    8/7
    3
    112
    7/9
    1
    50
  • Licensees – transfers

    Licensees – transfers
    Date valid from
    Transfer direction
    Type of change
    Company name
    Transferred interest [%]
    03.11.2022
    TO
    TRANSFER
    30.000000
    FROM
    TRANSFER
    30.000000
    30.09.2022
    TO
    CHANGE OF COMPANY NAME
    30.000000
    FROM
    CHANGE OF COMPANY NAME
    30.000000
    31.05.2022
    FROM
    TRANSFER
    40.000000
    TO
    TRANSFER
    40.000000
    19.12.2019
    TO
    TRANSFER
    15.000000
    FROM
    TRANSFER
    15.000000
    21.05.2019
    TO
    CHANGE OF COMPANY NAME
    15.000000
    FROM
    CHANGE OF COMPANY NAME
    15.000000
    04.12.2018
    TO
    TRANSFER
    40.000000
    FROM
    TRANSFER
    40.000000
    22.12.2017
    TO
    CHANGE OF COMPANY NAME
    40.000000
    FROM
    CHANGE OF COMPANY NAME
    40.000000
    09.12.2016
    FROM
    TRANSFER
    15.000000
    TO
    TRANSFER
    15.000000
    13.02.2013
    TO
    CHANGE OF COMPANY NAME
    15.000000
    FROM
    CHANGE OF COMPANY NAME
    15.000000
    28.02.2011
    TO
    CHANGE OF COMPANY NAME
    30.000000
    FROM
    CHANGE OF COMPANY NAME
    30.000000
    01.01.2009
    FROM
    TRANSFER
    15.000000
    TO
    TRANSFER
    15.000000
  • Status reports

    Status reports
    Document name
    Document format
    Document size [MB]