Phases
Phases Date phase valid fromDate phase valid toPhase02.03.201802.03.2023INITIAL03.03.202302.09.2023INITIAL EXTENDED03.09.202302.09.2043PRODUCTION -
Licensees — current
Licensees — current Date valid fromCompany longnameInterest [%]26.09.202440.000000-30.000000-30.000000 -
Operatorship — current
Operatorship — current Date valid fromCompany longname12.10.2021 -
Area – current
Area – current Date valid fromBlock namePolygon numberPolygon area
[km2]Vertical limitations03.09.20236507/2181-6507/1233 -
Work program (initial phase)
Work program (initial phase) Work obligationDecisionTask statusExpiry dateWellbore if drilledDrill firm exploration wellApproved02.03.20206507/2-5 S(BoK) Decision to concretizeApproved02.06.2021Conceptual studiesApproved(BoV) Decision to continueApproved02.09.2022(PDO) Prepare plan for developmentApproved(PDO) Submit plan for developmentApproved02.09.2023Decision to enter extension periodApproved02.09.2023 -
Conditions (production phase)
Conditions (production phase) Work taskDecisionDescription (norwegian)Task statusExpiry dateDecision to drillØrn NordWill be drilled02.03.2025(BoK) Decision to concretizeØrn NordDropped02.03.2026Drill exploration wellØrn NordApproved(BoV) Decision to continueØrn NordDropped02.03.2027Conceptual studiesØrn NordDroppedDecision to drillØrn ØstIn process02.03.2028Decision to drillØrn VestIn process02.03.2028(PDO) Submit plan for developmentØrn NordDropped02.03.2028(PDO) Prepare plan for developmentØrn NordDropped(BoK) Decision to concretizeØrn ØstIn process02.03.2029(BoK) Decision to concretizeØrn VestIn process02.03.2029Drill exploration wellØrn ØstIn processDrill exploration wellØrn VestIn process(BoV) Decision to continueØrn VestIn process02.03.2030(BoV) Decision to continueØrn ØstIn process02.03.2030Conceptual studiesØrn VestIn processConceptual studiesØrn ØstIn process(PDO) Submit plan for developmentØrn VestIn process02.03.2031(PDO) Submit plan for developmentØrn ØstIn process02.03.2031(PDO) Prepare plan for developmentØrn VestIn process(PDO) Prepare plan for developmentØrn ØstIn process -
Mortgages from the Petroleum register – current (in Norwegian only)
Mortgages from the Petroleum register – current (in Norwegian only) Dokument nummerRegistreringsdatoUtdrag av dokument1836213.03.2024PGNiG Upstream Norway AS pantsetter sin 40 % deltakerandel i tillatelsen til fordel for Societe Generale.Pantobligasjon stor USD 1 200 000 000, skriver United States Dollars one billion two hundred million.Pantsetter har ikke rett til å overdra eller foreta ytterligere pantsettelser av pantsatte objekt uten skriftlig samtykke fra panthaver.Energidepartementet har i brev av 20.11.2023 gitt samtykke i medhold av petroleumsloven § 6-2 første ledd. Pantsettelsen utgjør et såkalt krysspant. -
Wellbores – exploration, drilled in the production licence
Wellbores – exploration, drilled in the production licence Wellbore nameEntered dateCompleted datePurposeStatusContent23.07.201914.09.2019WILDCATP&AGAS09.02.202521.03.2025WILDCATP&ADRY -
Wellbores – development, drilled in the production licence
Wellbores – development, drilled in the production licence Wellbore nameEntered dateCompleted datePurpose - plannedStatusContent10.12.2025PRODUCTIONONLINE/OPERATIONAL11.12.2025PRODUCTIONONLINE/OPERATIONAL -
Wellbores – other, drilled in the production licence
Wellbores – other, drilled in the production licence Wellbore nameEntered dateCompleted datePurposeStatus06.06.202307.06.2023SHALLOW GASPLUGGED27.07.202429.07.2024SHALLOW GASP&A08.02.202508.02.2025SHALLOW GASPLUGGED -
Licensees — full history
Licensees — full history Date valid fromDate valid toCompany longnameInterest [%]26.09.202440.00000030.00000030.00000031.08.202225.09.202440.00000030.00000030.00000029.10.202130.08.202240.00000030.00000030.00000016.05.201828.10.202140.00000030.00000030.00000002.03.201815.05.201840.00000030.00000030.000000 -
Operatorship — full history
Operatorship — full history Date valid fromDate valid toCompany longname12.10.202116.05.201811.10.202102.03.201815.05.2018 -
Area – full history
Area – full history Date valid fromDate valid toBlock namePolygon numberPolygon area
[km2]Vertical limitations03.09.20236507/21816507/123302.03.201802.09.20236507/11516507/2299 -
Licensees – transfers
Licensees – transfers Date valid fromTransfer directionType of changeCompany nameTransferred interest [%]26.09.2024FROMCHANGE OF COMPANY NAME40.000000TOCHANGE OF COMPANY NAME40.00000031.08.2022TOTRANSFER40.000000FROMTRANSFER40.00000029.10.2021FROMTRANSFER10.000000TOTRANSFER10.00000016.05.2018TOCHANGE OF COMPANY NAME40.000000FROMCHANGE OF COMPANY NAME40.000000 -
Status reports
Status reports Document nameDocument formatDocument size [MB]