Give whole or part of name of wellbore, licence, field, company, discovery etc. E.g. Aker, Statfjord, 24/12, ABP21014. The main content is not searched.
Official name of wellbore based on Norwegian Offshore Directorate guidelines for designation of wells and wellbores.
26/10-1
Type
Wellbore type. Legal values: EXPLORATION, DEVELOPMENT, OTHER (see 'Purpose' for more information)
EXPLORATION
Purpose
Final classification of the wellbore.
Legal values for exploration wellbores:
WILDCAT, APPRAISAL, WILDCAT-CCS, APPRAISAL-CCS.
Legal values for development wellbores:
OBSERVATION, PRODUCTION, INJECTION, INJECTION-CCS, OBSERVATION-CCS.
Legal values for other wellbores:
SOIL DRILLING (drilling in connection with track surveys and other subsurface surveys to investigate the soil conditions prior to placement of facilities),
SHALLOW GAS (drilling to investigate shallow gas before the first 'real' drilling on the location),
PILOT (drilling to investigate the geology and fluid connectors for location of the main wellbore),
SCIENTIFIC (drilling according to Law of Scientific research and exploration),
STRATIGRAPHIC (driling according to Law of Petroleum activities §2-1).
WILDCAT
Status
Status for the wellbore. Legal values are:
BLOWOUT: A blowout has occurred in the well.
CLOSED: A development wellbore that has been closed in a shorter or longer periode. Also applies to development wellbores where drilling is completed, but production/injection has not yet been reported.
DRILLING: The well is in the drilling phase - can be active drilling, logging, testing or plugging,
JUNKED: The drilling operation has been terminated due to technical problems.
P&A: Exploration: The well is plugged and abandoned, and can not be reentered for further use. Development wells: The production/injection from/to the well is stopped and the well is plugged. The wellhead is removed or else made unavailable for further well operations.
PLUGGED: The wellbore has been plugged, but the upper parts of the wellbore can be re-used. A sidetrack might be drilled at a later stage.
PRODUCING: It was produced from the wellbore at the time of the operators last monthly report to the Norwegian Offshore Directorate.
INJECTING: It was injected to the wellbore at the time of the operators last monthly report to the Norwegian Offshore Directorate.
PREDRILLED: The upper part of the well has been drilled, usually as part of a batch-drilling campaign covering several wellbores.
RE-CLASS TO DEV: Exploration wellbore that is reclassified to a development wellbore.
RE-CLASS TO TEST: Exploration wellbore that is reclassified to test production.
SUSPENDED: The drilling operation in the wellbore has been temporarily stopped. The current plan is to continue drilling later on.
Indicator telling if the parent well is multilateral, meaning it has more than one branch radiating from the main borehole. Example of legal values: YES, NO. See also Norwegian Offshore Directorate guidelines for designation of wells and wellbores.
Name of the licensee starting the drilling operation on behalf of the active production license (well head position). This will usually equal the operator of the production license.
Lundin Norway AS
Drill permit
The drilling permit number together with the version of the drilling permit as stated in the drilling permit granted by the Norwegian Offshore Directorate.
1550-L
Drilling facility
Norwegian Offshore Directorate's name of the facility which the wellbore was drilled from.
Number of days from wellbore entry to wellbore completion.
25
Entered date
The date when he wellbore was spudded. For sidetracks: The date when new formation was drilled by kicking off from the mother-wellbore,
20.01.2015
Completed date
Exploration wellbores from moveable facilities:
For floating facilities - date when anchor handling is started. For jackups - date the jacking-down started. Exploration wellbores from fixed facilities and all development wellbores:
Date when the wellbore is at total depth, and last casing, liner or screen is set. In case of immediate plugging of the wellbore, completed date equals the date the last plug i set in the wellbore.
Date when the wellbore is at total depth, and last casing, liner or screen is set. In case of immediate plugging of the wellbore, completed date equals the date the last plug i set in the wellbore.
13.02.2015
Release date
Date when raw data which has been reported to the authorities from the wellbore is not confidential any longer. Normally 2 years after finishing the drilling. May be earlier if the area of the production license is relinquished.
13.02.2017
Publication date
Date quality control of the wellbore information was completed, so it can be published on the internet as a 'Well Data Summary Sheet' wellbore with more information available than other wellbores.
13.02.2017
Purpose - planned
Pre-drill purpose of the wellbore. Legal values for exploration wellbores: WILDCAT, APPRAISAL, WILDCAT-CCS, APPRAISAL-CCS. Example of legal values for development wellbores: OBSERVATION, PRODUCTION, INJECTION.
WILDCAT
Content
For exploration wellbores, status of discovery.
Legal values:
DRY, SHOWS (trace amounts of hydrocarbons), GAS, GAS/CONDENSATE, OIL or OIL/GAS.
SHOWS (GAS SHOWS, OIL SHOWS or OIL/GAS SHOWS) are detected as fluorescent cut (organic extract), petroleum odour, or visual stain on cuttings or cores, or as increased gas reading on the mud-loggers gas detection equipment. Legal values for WILDCAT-CCS and APPRAISAL-CCS: WATER
For development wellbores, type of produced/injected fluid.
Legal values:
WATER, CUTTINGS, NOT AVAILABLE, OIL, GAS/CONDENSATE, OIL/GAS, CO2, GAS, WATER/GAS, NOT APPLICABLE.
GAS
Discovery wellbore
Indicator which tells if the wellbore made a new discovery. Legal values: YES, NO. Prior to press-release or other information regarding drilling results, the indicator will be “NO” as a default.
YES
1st level with HC, age
Age of lithostratigraphic unit, 1st level, where hydrocarbons were encountered. Examples of legal values: CRETACEOUS, EARLY CRETACEOUS, LATE JURASSIC, EOCENE.
See also Norwegian Offshore Directorate bulletins.
MIOCENE
1st level with HC, formation
Name of lithostartigraphic unit, 1st level, where hydrocarbons were encountered. Shown only for released wells. Examples of legal values: BASEMENT, COOK FM, EKOFISK FM, HEIMDAL FM, SANDNES FM, SOGNEFJORD FM, TARBERT FM, BRENT GP.
See also Norwegian Offshore Directorate bulletins.
UTSIRA FM
Kelly bushing elevation [m]
Elevation of the rotary kelly bushing (RKB) above mean sea level.
30.0
Water depth [m]
Depth in metres betweem mean sea level and sea floor.
140.0
Total depth (MD) [m RKB]
Total measured length of wellbore from kelly bushing to total depth (driller's depth).
1025.0
Final vertical depth (TVD) [m RKB]
Vertical elevation from total depth to kelly bushing. Shown only for released wells. Referred to as true vertical depth (TVD).
1025.0
Maximum inclination [°]
Maximum deviation, in degrees, from a vertical well path.Shown only for released wells.
1.5
Oldest penetrated formation
Name of the oldest lithostratigraphic unit penetrated by the wellbore. Shown only for released wells. In most wellbores this is formation or group at total depth. May differ from formation or group at TD for example in wellbores drilled with high deviation or through faults. Examples of legal values: AMUNDSEN FM, BALDER FM, BASEMENT, BLODØKS FM, BRYNE FM, BURTON FM, COOK FM, DRAKE FM, DRAUPNE FM, EKOFISK FM, DUNLIN GP.
HORDALAND GP
Geodetic datum
Reference system for coordinates. Example of legal values: ED50.
ED50
NS degrees
Geographic coordinate of the wellhead, north-south degrees.
59° 0' 1.87'' N
EW degrees
Geographic coordinate of the wellhead, east-west degrees.
3° 4' 14.7'' E
NS UTM [m]
Universal Transverse Mercator coordinate of the wellhead, north-south.
6540262.79
EW UTM [m]
Universal Transverse Mercator coordinate of the wellhead, east-west.
Well 26/10-1 was drilled to test the Zulu Øst prospect on Patch Bank Ridge south of the Stord Basin in the North Sea. The prospect is a fan complex consisting of Miocene age sands and sandstones of the Utsira Formation. The primary objective was to evaluate the reservoir properties of these sands and to prove presence of hydrocarbons.
Operations and results
Wildcat well 26/10-1 was spudded with the semi-submersible installation Island Innovator on 20 January 2015 and drilled to TD at 1025 m in Early Miocene sediments belonging to the Hordaland Group. No significant problem was encountered in the operations. The well was drilled with seawater and high viscosity pills down to 290 m and with Aquadril mud from 290 m to TD.
Three massive Miocene sands were penetrated by the well, all three with very good reservoir properties. Average porosity for the three sands is 35 to 36%. The topmost, Utsira Formation sandstone, was penetrated at 802.5 m, and proved gas filled down to its base at 825.5 m. Pressure gradient data show a distinct gas-water contact at 838 m. The gas is dry (99.7% methane) and the stable carbon isotopic composition of the methane is light (d13C = -71.3 ppt VPDB). These characteristics are typical for biogenic gas. The two other sands were water filled. No oil shows were recorded in the well.
No cores were cut. MDT fluid samples were taken at 811.6 m (gas) and 874.6 (water).
The well was permanently abandoned on 13 February 2015 as a gas discovery.